Follow on:

Hewa Khola A Small Hydropower Project (7.5 MW)

Hewa Khola A Small Hydropower Project (7.5 MW)

Power Purchase Agreement (PPA)

07-10-2075 (B.S.); 21-01-2019 (A.D.)

Grid Connection Agreement

24-06-2080 (B.S.); 11-10-2023 (A.D.)

Generation License

14-04-2075 (B.S.); 30-07-2018 (A.D.)

Financial Agreement

09-10-2079 (B.S.); 23-01-2023 (A.D.)

Financial Partners

Machhapuchchhre Bank Limited (Lead), Lumbini Bikas Bank Limited

Design Consultant

Clean Energy Consultants (P) Ltd.

Technical Consultant from the Bank

Technoquarry Consults Pvt. Ltd.

Financial Analyst

Mr. Narayan Poudel, CA

Financial Consultants from the Bank

S Subedi & Associates

Financial Consultant from the Company

Mr. Ramsharan Giri, CA

Hewa Khola A Small Hydropower Project (7.5 MW)
Hewa Khola A Small Hydropower Project (7.5 MW)

Overview

Located in Falelung Rural Municipality, Panchthar district, Province no. 1, Eastern Nepal, Hewa A Small Hydropower Project is a run-of-river (RoR) type with a capacity of 7.5 MW. The project’s design discharge and gross head are 4.95 m3/sec and 204.8 m respectively. Situated on the left bank of Hewa Khola, a tributary of Tamor River, the project area’s coordinates are between Longitudes 87º51’00” E and 87º53’15” E, Latitudes 27010’40” N and 27011’38” N. Its major components include river diversion, headworks, gravel trap, desander, forebay, headrace, penstock, powerhouse, and tailrace canal. The project is accessible via Kathmandu-Phidim-Yagnam road, with a total distance of approximately 770km, and the nearest airports are Suketar and Bhadrapur Airport.

The transmission line is connected to the national grid through a 33KV transmission line, which passes through the HKSHP Switchyard area and extends for 10km to reach the 33kv/132KV NEA Substation at Thapatar, Phidim Panchthar.

Devastating Flood Causes Extensive Damage to Project Site
On June 2, 2023 (Ashad 02, 2080), a massive catastrophic flood occurred in Hewa Khola, causing extensive damage to the project.
This flood was the most severe to date and had a significant impact, particularly on the headwork site, including the Powerhouse, Weir, Gravel Trap, and Desander basin. The flood swept away various ongoing construction works, including excavation, soling, and PCC at the Weir, Desander, and Intake sites.

Additionally, the excavation works at the Powerhouse, which were 70% complete at the time, were also washed away. Infrastructure such as a 150KVA transformer, construction power equipment, and access roads suffered damage and required full repair and maintenance due to heavy rainfall, landslides, and soil erosion. Significant losses included the civil contractor camp, an excavator, a 30KVA DG, and transformers (100KVA and 150KVA), along with partial damage to two excavators and one bike. Thankfully, there were no human casualties.

Before

Hewa Khola A Small Hydropower Project (7.5 MW)

After

Hewa Khola A Small Hydropower Project (7.5 MW)

Salient Features

1 Project Location
Province Koshi
District Panchthar
Intake Site Papundin
Powerhouse Site Yanyeppa
Geographical Co-ordinates
Latitude 27˚ 10’ 40’’ N to 27˚ 11’ 38’’ N
Longitude 87˚ 51’ 00’’ E to 87˚ 53’ 26’’ E
Conservation Area n/a
2 General
Name of River Hewa Khola and Niwa Khola
Nearest Settlement Phidim Bazaar
Type of Scheme Run-of-river
Gross Head 204.8 m
Net rated Head 175.31
Installed Capacity 7.5 MW
Peak Hour (if P-RoR) N/A
Average Annual Energy after Outage 48.42 GWh
Deemed Wet Energy 30.91 GWh
Deemed Dry Energy 17.51 GWh
3 Hydrology
Catchment Area 162.08 km2
Hewa Intake= 139.88 km
Niwa Intake= 22.20 km
Average Annual Discharge 10.33
Minimum Monthly Discharge 2.02
Maximum Monthly Discharge 27.68
Design Discharge (at 40% PoE) 4.95m3/s
Hewa Intake= 4.10 m/s
Niwa Intake= 0.85 m/s
Design Flood Discharge For Hewa Intakes: 495 m3/s
For powerhouse: 637 m3/s
Average Annual Precipitation 2255.05 mm
4 Hewa Headworks
Type of Weir Free Flow Gravty Weir
Length of Weir 20.05 m
Crest Elevation 1138.00 masl
No. of Undersluice Opening 1 no.
Size (W x H)/td> 3.00 m x 3.00 m
Type of Intake Side Intake
No. of Intake Opening 3 nos.
Size of Intake Orifice (W x H) 2.00 m x 1.00 m
Intake Invert Level 1137.00 masl
5 Niwa Headworks
Type of Weir Free Flow Gravty Weir
Length of Weir 16.06 m
Crest Elevation 1142.80 masl
No. of Undersluice Opening 1 no.
Size (W x H)/td> 2.00 m x 1.85 m
Type of Intake Side Intake
Size of Intake Orifice (W x H) 1.50 m x 0.85 m
Intake Invert Level 1141.64 masl
6 Gravel Trap
Length 25.00 m
Width and Depth 7.20 m x 3.7 m avg.
Slope 1:6 in transition and 1:10 in main section
7 Connecting Canal
Length 162.56 m
Size (W x H) 2.40 m x 2.30 m
Invert Level at Exit 1135.88 masl
8 Desanding Basin
Type 3-bay, Dufour Single Chamber Type
Dimension (L x B x H) 50.02 m x 5.00 m x 4.5 m avg
Length of Inlet Transition 9.98 m
Particle Size to be Settled 0.20 mm
Settling Criteria 5000 ppm
Settling Efficiency 92%
9 Headrace Pipe
Type IS 2062-BO, E350 MPa
Internal Diameter 1.55 m, 1.45 m & 1.35 m
Length 3888.23 m upto Surge Junction
Thickness 7mm
10 Surge Pipe
Type Inclined Pipe buried on ground
Internal Diameter 1.55 m, 1.45 m & 1.35 m
Length 3.00 m
Thickness 10 mm
Upsurge Level 1158.20 masl
Downsurge Level 1107.40 masl
Static Level 1137.73 masl
11  Steel Penstock Pipe 
Type Steel Lined Penstock, open/buried (Confirming to IS 2062 BO, E350)
Internal Diameter 1.30 m
Length 413.43 m e
Minimum Steel Thickness 14 mm
No. of Anchor Blocks 9 nos.
12   Powerhouse
Type Sub-surface
Size (L x W) 38.30 m x 11.40 m
Height 18.88 m from Machine floor level to the roof
Switchyard Outdoor
10               Tailrace Canal
Type RCC, Box Culvert Free flow type
Length of Tailrace 3.55 m
Tail Water Level 930.00 masl
11               Turbine
Type Horizontal axis Pelton
Number 3 nos.
Rated Output Capacity per unit 2600 KW
Center line of turbine 933.2 masl
Efficiency 92%
15 Governor
Type Electronic PID Control
Adjustment for Speed Drop Between 0-5%
16  Generator
Type 3-phase AC synchronous
Rated Output Capacity per Unit 2941 KVA
Power Factor 0.85 pf generation
Voltage 6.6 kV
Frequency 50 Hz
No of Units 3 nos.
Excitation System Brushless excitation
Efficiency 97%
17 Transformer
Type Outdoor step-up power transformer, Three Phase
Rated Capacity 9000 kVA
Voltage Levels 6.6/33 (Secondary/Primary)
No of Units 1 no.
Vector Group YNd11
Efficiency 99%
18  Transmission Line 
Voltage Level 33 kV Length
10 Km Conductor
ACSR” DOG”
From Power plant switchyard
To 33/132 kV Thapatar Substation
Delivery Point 33 kV Busbarn